More bricks
The scaffolding was pulled down and more bricks were delivered making the brick total 30 pallets or 12000 bricks wowsers!
back view to alfresco - you can see the edge of the pool to the left
more bricks
more bricks
bricks around the right...
bricks around the left
no ugly scaffolding...woohoo I can see my beautiful pavilion taking shape
bricks out the front
Tuesday, 20 August 2013
Bricks & Plumbing
With all the frames complete now, today saw the delivery of the bricks and all the plumbing rough-in was done. Bradnams also installed our bi-fold doors (I've been waiting soooooo long to see these) to see the meals/family rooms and boy, they didn't disappoint!
my gorgeous bi-folds games/meals
ens
alfresco
look...bricks!
more bricks...
more bricks
Thursday, 15 August 2013
Frame complete
We finally have all the frames completed and it looks awesome. All the coffered ceilings are done along with the drop down ceiling in the kitchen. All the bulkheads are done as well as the bath frames. We know how hard these guys have worked and trust me, with the system like ours, they need a medal. Because we are having roof tiles instead of colourbond, our frame had to be strengthened in order to bare the weight of the tiles. Usually if you are having tiles, you have a timber frame but we paid extra to have the strength of steel hence the longer build time.
drop down ceiling in kitchen
Monday, 12 August 2013
The roof
They installed the roof trusses this morning and boy was it great to watch...what a great job. Now it's looking like a real house and not a leggo system
Friday, 9 August 2013
Scaffolding
Some scaffolding was set up out the front today, I'm guessing it's to make it easier for the guys to put the trusses on the pavilion and for when the tiles go on the roof...maybe!!
Monday, 5 August 2013
The window to my soul
The windows were next to go in and I couldn't be more ecstatic they look awesome, I'm so glad I chose the colour I'm very happy
the left (dead) side of the home
front left side
Thursday, 1 August 2013
Truss me!
They put some roof trusses on the alfresco and garage and stood some more walls up. We got to meet our SS this afternoon and boy is he a nice man.
We went through the house to make sure we were happy with it (of course we were) and he told us that everything was going well with the build and because it was a big home, it was going to take longer than most other builds.
As long as we're in by xmas, I'll be a happy camper!
We went through the house to make sure we were happy with it (of course we were) and he told us that everything was going well with the build and because it was a big home, it was going to take longer than most other builds.
As long as we're in by xmas, I'll be a happy camper!
alfresco
Wednesday, 31 July 2013
More walls
Next to go up were the garage walls and alfresco
meter box with 3phase power
triple car garage with external access
The alfresco (pool to the right)
Tuesday, 30 July 2013
The Meccano Set!
They stood the first lot of frames up today and we almost have a house yippee. This has been a long time coming and finally we get to see for ourselves the beginning of our 'Resort'
garages
front entry
right side of house...courtyard
Friday, 26 July 2013
Windows
We had our windows delivered today. I've been hanging out for these babies and they're finally here woo hoo. Now just hanging to see them in I can't wait
Wednesday, 24 July 2013
Frame delivery
Frames delivered, Kordon termite barrier sprayed and hooked up to electricity...ready for take off!
right side of house where the courtyard will be, which will house the garden shed/pool equipment
my frames
check out the view behind the trees...awesome!
frames...
and more frames
Friday, 19 July 2013
Set in stone!
We now have concrete...yay
I know I wasn't support to be here (safety reasons and all) I mean it is a construction site!, but who could resist watching their home grow when they've waited sooooooo long for things to start ha?????
I know I wasn't support to be here (safety reasons and all) I mean it is a construction site!, but who could resist watching their home grow when they've waited sooooooo long for things to start ha?????
they started on the garage side just before I got there after taking the kids to school
towards the rear of the house now and coming up to the alfresco and master bed now
doing the alfresco area and contemplating on wether they need another load!
yep, another load was needed to finish off the master bed
ta da...complete and the boards had been taken off by the time I got back from picking the boys up from school
Thursday, 18 July 2013
Waffle on!
After having heavy showers yesterday, we finally saw our waffle pods laid and are now ready to be concreted
Tuesday, 16 July 2013
Saturday, 13 July 2013
Piering
The piering was done today 62 all up (tender was 60) with only having to drill 2 of the back ones deeper because of the proximity of the pool @ an extra $160 cheering!
Tuesday, 9 July 2013
Plumbing
We had the plumbing done at the site today and our electrical appointment which went very smoothly and was over in about 2 hours.